Dept. of Trans. PROGRESS Serial No. Contract No. 20-206-09-12 07-301504 PROGRESS PAYMENT VOUCHER %complete: %time: 57% 60% Location: Federal Project: 07-LA-10-R2.1/18.4 ACIM-010-1(844) Progress payment No. 016 Payment period ending: 07-20-20 SECURITY PAVING COMPANY INC 3075 TOWNSGATE RD #200 WESTLAKE VILLAGE CA 91361 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 13,530,688.66 1,605,721.77 2. a. Extra Work 105,829.84 21,787.82 b. Adustment Comp. 434,445.74 434,445.74 3. Materials on Hand 55,960.00 55,960.00 4. Earned Subject to Retention 14,126,924.24 2,117,915.33 5. Mobilization 1,828,944.28 0.00 6. Total Work Completed 15,899,908.52 7. Deductions -30,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 15,925,868.52 2,117,915.33 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,117,915.33