Dept. of Trans. PROGRESS Serial No. Contract No. 25-080-07-45 07-301604 PROGRESS PAYMENT VOUCHER %complete: %time: 3% 12% Location: Federal Project: 07-VAR BFNH-X037(236) Progress payment No. 003 Payment period ending: 03-20-25 POWELL CONSTRUCTORS INC 8555 BANANA AVE FONTANA CA 92335 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 375,580.00 101,950.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 375,580.00 101,950.00 5. Mobilization 6. Total Work Completed 375,580.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 375,580.00 101,950.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 101,950.00