Dept. of Trans. PROGRESS Serial No. Contract No. 25-201-15-53 07-301604 PROGRESS PAYMENT VOUCHER %complete: %time: 12% 33% Location: Federal Project: 07-VAR BFNH-X037(236) Progress payment No. 007 Payment period ending: 07-20-25 POWELL CONSTRUCTORS INC 8555 BANANA AVE FONTANA CA 92335 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,036,548.10 56,250.00 2. a. Extra Work 12,806.04 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 1,049,354.14 56,250.00 5. Mobilization 660,755.00 0.00 6. Total Work Completed 1,710,109.14 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,710,109.14 56,250.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 56,250.00