Dept. of Trans. PROGRESS Serial No. Contract No. 20-080-16-28 07-301904 PROGRESS PAYMENT VOUCHER %complete: %time: 17% 10% Location: Federal Project: 07-LA-210-R33.1/R44.1 HSIM-210-1(852) Progress payment No. 002 Payment period ending: 03-20-20 CHUMO CONSTRUCTION INC 14425 JOANBRIDGE ST BALDWIN PARK CA 917061747 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 167,220.17 147,735.17 2. a. Extra Work 6,641.50 6,641.50 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 173,861.67 154,376.67 5. Mobilization 127,500.00 127,500.00 6. Total Work Completed 301,361.67 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 301,361.67 281,876.67 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 281,876.67