Dept. of Trans. PROGRESS Serial No. Contract No. 23-023-10-34 07-302404 PROGRESS PAYMENT VOUCHER %complete: %time: 58% 69% Location: Federal Project: 07-VEN-101-R36.3/R40.6 B1NH-Q101(385) Progress payment No. 022 Payment period ending: 01-20-23 GRANITE CONSTRUCTION COMPANY PO BOX 50085 WATSONVILLE CA 95077 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,624,804.72 89,626.00 2. a. Extra Work 10,745,089.10 676,536.40 b. Adustment Comp. 833,894.16 187,078.41 3. Materials on Hand 3,063,016.37 0.00 4. Earned Subject to Retention 18,266,804.35 953,240.81 5. Mobilization 3,200,000.00 0.00 6. Total Work Completed 18,403,787.98 7. Deductions -6,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 21,460,804.35 953,240.81 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 953,240.81