Dept. of Trans. PROGRESS Serial No. Contract No. 21-081-15-39 07-302504 PROGRESS PAYMENT VOUCHER %complete: %time: 51% 35% Location: Federal Project: 07-VEN-23-R3.3/R11.5 HSST-P023(41) Progress payment No. 013 Payment period ending: 03-20-21 SECURITY PAVING COMPANY INC 3075 TOWNSGATE RD #200 WESTLAKE VILLAGE CA 91361 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 31,546,852.42 4,379,245.48 2. a. Extra Work 837,779.69 144,138.72 b. Adustment Comp. 2,759.27 2,759.27 3. Materials on Hand 848,452.00 -43,195.00 4. Earned Subject to Retention 33,235,843.38 4,482,948.47 5. Mobilization 3,400,000.00 170,000.00 6. Total Work Completed 35,787,391.38 7. Deductions -94,600.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 36,541,243.38 4,652,948.47 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 4,652,948.47