Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 25-170-14-24 07-302504 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 07-VEN-23-R3.3/R11.5 HSST-P023(41) Progress payment No. 050 Payment period ending: 10-21-24 SECURITY PAVING COMPANY INC 3075 TOWNSGATE RD #200 WESTLAKE VILLAGE CA 91361 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 53,371,185.01 466,321.50 2. a. Extra Work 9,513,681.58 242,364.58 b. Adustment Comp. 1,607,830.53 -321,625.73 3. Materials on Hand 4. Earned Subject to Retention 64,492,697.12 387,060.35 5. Mobilization 3,400,000.00 0.00 6. Total Work Completed 67,892,697.12 7. Deductions -41,600.00 -20,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 67,851,097.12 367,060.35 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 367,060.35