Dept. of Trans. PROGRESS Serial No. Contract No. 22-231-14-16 07-304504 PROGRESS PAYMENT VOUCHER %complete: %time: 58% 46% Location: Federal Project: 07-LA-57-R0.0/R4.5 HSNH-P057(69) Progress payment No. 024 Payment period ending: 08-20-22 GRIFFITH VANGUARD JOINT VENTURE 12200 BLOOMFIELD AVE SANTA FE SPRINGS CA 90670 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 28,595,091.65 3,955,118.44 2. a. Extra Work 1,517,205.88 56,802.52 b. Adustment Comp. 915,752.29 3,371.09 3. Materials on Hand 235,693.57 0.00 4. Earned Subject to Retention 31,263,743.39 4,015,292.05 5. Mobilization 5,300,000.00 265,000.00 6. Total Work Completed 36,328,049.82 7. Deductions -4,000.00 11,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 36,559,743.39 4,291,292.05 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 4,291,292.05