Dept. of Trans. PROGRESS Serial No. Contract No. 23-142-09-11 07-304804 PROGRESS PAYMENT VOUCHER %complete: %time: 65% 61% Location: Federal Project: 07-LA-405-8.8/8.8 NONE Progress payment No. 006 Payment period ending: 05-20-23 FEC FUTURE CONTRACTORS AND ENGINEERS INC 184 TECHNOLOGY DRIVE #205 IRVINE CA 92618 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,271,639.45 314,139.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 60,168.00 -90,562.00 4. Earned Subject to Retention 1,331,807.45 223,577.00 5. Mobilization 187,950.00 0.00 6. Total Work Completed 1,459,589.45 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,519,757.45 223,577.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 223,577.00