Dept. of Trans. PROGRESS Serial No. Contract No. 20-170-19-46 07-304904 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 51% Location: Federal Project: 07-LA-1-39.2/55.7 NONE Progress payment No. 004 Payment period ending: 06-20-20 YAKAR 689 EAST SAN BERNARDINO RD COVINA CA 91723 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 607,724.00 25,171.00 2. a. Extra Work 8,569.55 8,569.55 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 616,293.55 33,740.55 5. Mobilization 45,000.00 0.00 6. Total Work Completed 661,293.55 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 661,293.55 33,740.55 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 33,740.55