Dept. of Trans. PROGRESS Serial No. Contract No. 17-332-11-47 07-306204 PROGRESS PAYMENT VOUCHER %complete: %time: 66% 88% Location: Federal Project: 07-LA-91-R11.3/R20.7 NHP-P091(142) Progress payment No. 018 Payment period ending: 11-20-17 USS CAL BUILDERS INC 8051 MAIN ST STANTON CA 90680 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,704,557.34 886,508.49 2. a. Extra Work 124,289.52 13,716.71 b. Adustment Comp. 3. Materials on Hand 98,199.38 -27,471.10 4. Earned Subject to Retention 9,927,046.24 872,754.10 5. Mobilization 615,678.00 0.00 6. Total Work Completed 10,444,524.86 7. Deductions -243,470.78 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 10,299,253.46 862,754.10 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 862,754.10