Dept. of Trans. PROGRESS Serial No. Contract No. 17-268-11-13 07-306404 PROGRESS PAYMENT VOUCHER %complete: %time: 46% 55% Location: Federal Project: 07-LA-210-24.7/44.9 NHPI-210 1-830(E) Progress payment No. 016 Payment period ending: 09-20-17 SELECT ELECTRIC INC 2790 BUSINESS PARK DR VISTA CA 92081 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,676,934.85 432,179.03 2. a. Extra Work 101,076.90 0.00 b. Adustment Comp. 3. Materials on Hand 253,305.19 159,530.04 4. Earned Subject to Retention 5,031,316.94 591,709.07 5. Mobilization 798,436.05 0.00 6. Total Work Completed 5,576,447.80 7. Deductions 0.00 10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 5,829,752.99 601,709.07 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 601,709.07