Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 25-220-14-04 07-306614 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 07-LA-213-0.0/8.0 ACNH-P213(8) Progress payment No. 023 Payment period ending: 06-30-25 A M CONCRETE INC PO BOX 3367 THOUSAND OAKS CA 91359 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,022,400.75 641,738.10 2. a. Extra Work 361,778.40 16,558.13 b. Adustment Comp. 3. Materials on Hand 0.00 -297,311.84 4. Earned Subject to Retention 4,384,179.15 360,984.39 5. Mobilization 416,000.00 0.00 6. Total Work Completed 4,800,179.15 7. Deductions -10,000.00 -9,915.90 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 4,790,179.15 351,068.49 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 351,068.49