Dept. of Trans. PROGRESS Serial No. Contract No. 23-260-15-53 07-307024 PROGRESS PAYMENT VOUCHER %complete: %time: 35% 30% Location: Federal Project: 07-LA-107-0.4/4.8 ACNH-P107(17) Progress payment No. 004 Payment period ending: 09-20-23 CALPROMAX ENGINEERING INC 650 N ROSE DRIVE #186 PLACENTIA CA 92870 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 596,153.00 112,993.00 2. a. Extra Work 14,864.59 4,249.03 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 611,017.59 117,242.03 5. Mobilization 142,500.00 0.00 6. Total Work Completed 753,517.59 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 753,517.59 117,242.03 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 117,242.03