Dept. of Trans. FINAL Serial No. Contract No. 17-160-08-15 07-307304 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 07-LA-5-59.7/73.9 HSNH-PG X037-189(E) Progress payment No. 005 Payment period ending: 04-14-17 DREAMBUILDER CONSTRUCTION CORP 1324 E LAWSON LN PLACENTIA CA 92870 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 709,388.57 0.00 2. a. Extra Work 12,391.73 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 721,780.30 0.00 5. Mobilization 99,996.00 0.00 6. Total Work Completed 821,776.30 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 821,776.30 0.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 0.00