Dept. of Trans. PROGRESS Serial No. Contract No. 18-142-13-33 07-307604 PROGRESS PAYMENT VOUCHER %complete: %time: 41% 18% Location: Federal Project: 07-VEN-118-T19.1/R30.5 ACNH-P118(66) Progress payment No. 001 Payment period ending: 05-20-18 SECURITY PAVING COMPANY INC 13170 TELFAIR AVE SYLMAR CA 91342 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 256,953.05 256,953.05 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 256,953.05 256,953.05 5. Mobilization 114,950.48 114,950.48 6. Total Work Completed 371,903.53 7. Deductions -28,396.26 -28,396.26 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 343,507.27 343,507.27 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 343,507.27