Dept. of Trans. PROGRESS Serial No. Contract No. 18-204-14-12 07-307904 PROGRESS PAYMENT VOUCHER %complete: %time: 24% 18% Location: Federal Project: 07-LA-101-2.8/7.4 NONE Progress payment No. 002 Payment period ending: 07-20-18 STL LANDSCAPE INC 8122 COMPTON AVE LOS ANGELES CA 90001 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 45,570.00 40,895.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 45,570.00 40,895.00 5. Mobilization 15,000.00 15,000.00 6. Total Work Completed 60,570.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 60,570.00 55,895.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 55,895.00