Dept. of Trans. PROGRESS Serial No. Contract No. 18-234-14-42 07-307904 PROGRESS PAYMENT VOUCHER %complete: %time: 64% 43% Location: Federal Project: 07-LA-101-2.8/7.4 NONE Progress payment No. 003 Payment period ending: 08-20-18 STL LANDSCAPE INC 8122 COMPTON AVE LOS ANGELES CA 90001 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 144,740.00 99,170.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 144,740.00 99,170.00 5. Mobilization 20,000.00 5,000.00 6. Total Work Completed 164,740.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 164,740.00 104,170.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 104,170.00