Dept. of Trans. PROGRESS Serial No. Contract No. 18-264-14-01 07-307904 PROGRESS PAYMENT VOUCHER %complete: %time: 89% 68% Location: Federal Project: 07-LA-101-2.8/7.4 NONE Progress payment No. 004 Payment period ending: 09-20-18 STL LANDSCAPE INC 8122 COMPTON AVE LOS ANGELES CA 90001 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 184,235.00 39,495.00 2. a. Extra Work 10,408.45 10,408.45 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 194,643.45 49,903.45 5. Mobilization 20,000.00 0.00 6. Total Work Completed 214,643.45 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 214,643.45 49,903.45 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 49,903.45