Dept. of Trans. PROGRESS Serial No. Contract No. 16-173-13-06 07-308504 PROGRESS PAYMENT VOUCHER %complete: %time: 20% 24% Location: Federal Project: 07-VEN-23-R4.8/R11.4 NHP-X111(74) Progress payment No. 003 Payment period ending: 06-20-16 SERVITEK SOLUTIONS INC 636 BREA CANYON RD CITY OF INDUSTRY CA 91789 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 356,064.38 170,287.32 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 356,064.38 170,287.32 5. Mobilization 69,450.44 23,150.15 6. Total Work Completed 425,514.82 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 425,514.82 193,437.47 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 193,437.47