Dept. of Trans. PROGRESS Serial No. Contract No. 17-205-15-54 07-308504 PROGRESS PAYMENT VOUCHER %complete: %time: 89% 94% Location: Federal Project: 07-VEN-23-R4.8/R11.4 NHP-X111(74) Progress payment No. 015 Payment period ending: 07-20-17 SERVITEK SOLUTIONS INC PO BOX 13129 ATLANTA GA 30324 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,915,949.03 266,715.12 2. a. Extra Work 6,781.88 0.00 b. Adustment Comp. 3. Materials on Hand 0.00 -192,882.81 4. Earned Subject to Retention 1,922,730.91 73,832.31 5. Mobilization 92,600.58 0.00 6. Total Work Completed 2,015,331.49 7. Deductions -8,000.00 -8,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,007,331.49 65,832.31 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 65,832.31