Dept. of Trans. PROGRESS Serial No. Contract No. 16-208-08-53 07-308604 PROGRESS PAYMENT VOUCHER %complete: %time: 6% 26% Location: Federal Project: 07-LA-10-R2.1/R14.8 NHPI-X037(187) Progress payment No. 004 Payment period ending: 07-20-16 CROSSTOWN ELECTRICAL & DATA INC 5463 DIAZ ST IRWINDALE CA 91706 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 14,000.00 0.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 355,528.78 55,605.20 4. Earned Subject to Retention 369,528.78 55,605.20 5. Mobilization 135,000.00 0.00 6. Total Work Completed 149,000.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 504,528.78 55,605.20 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 55,605.20