Dept. of Trans. PROGRESS Serial No. Contract No. 20-204-13-42 07-309104 PROGRESS PAYMENT VOUCHER %complete: %time: 44% 59% Location: Federal Project: 07-LA-110-18.8/23.8 SNHG-P110(22) Progress payment No. 006 Payment period ending: 07-20-20 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,353,748.80 444,141.10 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 72,684.00 -118,501.77 4. Earned Subject to Retention 1,426,432.80 325,639.33 5. Mobilization 168,150.00 0.00 6. Total Work Completed 1,521,898.80 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,594,582.80 325,639.33 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 325,639.33