Dept. of Trans. PROGRESS Serial No. Contract No. 21-203-17-09 07-3096U4 PROGRESS PAYMENT VOUCHER %complete: %time: 39% 24% Location: Federal Project: 07-LA-210-R0.0/R9.7 NONE Progress payment No. 014 Payment period ending: 07-20-21 FLATIRON WEST, INC. 2100 GOODYEAR RD BENICIA CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 38,202,975.34 3,817,462.71 2. a. Extra Work 1,786,467.73 108,576.36 b. Adustment Comp. 297,254.41 0.00 3. Materials on Hand 2,819,537.94 -180,015.07 4. Earned Subject to Retention 43,106,235.42 3,746,024.00 5. Mobilization 12,477,775.00 0.00 6. Total Work Completed 52,764,472.48 7. Deductions -4,620.00 -4,620.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 55,579,390.42 3,741,404.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,741,404.00