Dept. of Trans. PROGRESS Serial No. Contract No. 22-234-11-27 07-3096U4 PROGRESS PAYMENT VOUCHER %complete: %time: 78% 48% Location: Federal Project: 07-LA-210-R0.0/R9.7 NONE Progress payment No. 028 Payment period ending: 08-20-22 FLATIRON WEST, INC. 12121 SCRIPPS SUMMIT DRIVE #4 SAN DIEGO CA 92131 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 90,623,784.34 3,826,379.57 2. a. Extra Work 3,028,752.55 -500,011.90 b. Adustment Comp. 3,514,534.24 362,945.74 3. Materials on Hand 972,689.53 -52,605.51 4. Earned Subject to Retention 98,139,760.66 3,636,707.90 5. Mobilization 13,134,500.00 0.00 6. Total Work Completed 110,301,571.13 7. Deductions -8,580.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 111,265,680.66 3,636,707.90 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,636,707.90