Dept. of Trans. PROGRESS Serial No. Contract No. 22-327-15-16 07-3096U4 PROGRESS PAYMENT VOUCHER %complete: %time: 86% 54% Location: Federal Project: 07-LA-210-R0.0/R9.7 NONE Progress payment No. 031 Payment period ending: 11-20-22 FLATIRON WEST, INC. 12121 SCRIPPS SUMMIT DRIVE #4 SAN DIEGO CA 92131 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 101,508,333.54 649,175.00 2. a. Extra Work 3,761,505.85 17,811.24 b. Adustment Comp. 4,629,797.48 160,347.86 3. Materials on Hand 622,876.82 -29,499.50 4. Earned Subject to Retention 110,522,513.69 797,834.60 5. Mobilization 13,134,500.00 0.00 6. Total Work Completed 123,034,136.87 7. Deductions -8,580.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 123,648,433.69 797,834.60 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 797,834.60