Dept. of Trans. PROGRESS Serial No. Contract No. 23-111-15-12 07-3096U4 PROGRESS PAYMENT VOUCHER %complete: %time: 93% 63% Location: Federal Project: 07-LA-210-R0.0/R9.7 NONE Progress payment No. 036 Payment period ending: 04-20-23 FLATIRON WEST, INC. 12121 SCRIPPS SUMMIT DRIVE #4 SAN DIEGO CA 92131 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 112,005,386.78 2,402,504.98 2. a. Extra Work 4,337,852.74 69,581.21 b. Adustment Comp. 7,207,185.04 861,807.50 3. Materials on Hand 359,387.57 -33,054.19 4. Earned Subject to Retention 123,909,812.13 3,300,839.50 5. Mobilization 13,134,500.00 0.00 6. Total Work Completed 136,684,924.56 7. Deductions -8,580.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 137,035,732.13 3,300,839.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,300,839.50