Dept. of Trans. PROGRESS Serial No. Contract No. 20-147-12-39 07-310804 PROGRESS PAYMENT VOUCHER %complete: %time: 78% 28% Location: Federal Project: 07-LA-14-R24.8/R31.4 ACNH-P014(80) Progress payment No. 003 Payment period ending: 05-20-20 IBARRA GENERAL ENGINEERING INC 4325 TYROLITE ST RIVERSIDE CA 92509 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,187,311.70 851,422.88 2. a. Extra Work 3,949.03 3,949.03 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 1,191,260.73 855,371.91 5. Mobilization 120,000.00 6,000.00 6. Total Work Completed 1,311,260.73 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,311,260.73 861,371.91 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 861,371.91