Dept. of Trans. PROGRESS Serial No. Contract No. 23-234-15-52 07-3114A4 PROGRESS PAYMENT VOUCHER %complete: %time: 55% 29% Location: Federal Project: 07-LA-101-1.7/6.8 HSNH-Q101(364) Progress payment No. 009 Payment period ending: 08-20-23 DIVERSIFIED LANDSCAPE COMPANY 21730 BUNDY CANYON RD WILDOMAR CA 92595 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 554,548.20 115,248.39 2. a. Extra Work 53,454.49 0.00 b. Adustment Comp. 12,182.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 620,184.69 115,248.39 5. Mobilization 17,480.00 0.00 6. Total Work Completed 637,664.69 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 637,664.69 115,248.39 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 115,248.39