Dept. of Trans. PROGRESS Serial No. Contract No. 23-296-17-42 07-3114A4 PROGRESS PAYMENT VOUCHER %complete: %time: 69% 37% Location: Federal Project: 07-LA-101-1.7/6.8 HSNH-Q101(364) Progress payment No. 011 Payment period ending: 10-20-23 DIVERSIFIED LANDSCAPE COMPANY 21730 BUNDY CANYON RD WILDOMAR CA 92595 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 829,963.15 131,942.00 2. a. Extra Work 53,454.49 0.00 b. Adustment Comp. 12,182.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 895,599.64 131,942.00 5. Mobilization 18,400.00 0.00 6. Total Work Completed 913,999.64 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 913,999.64 131,942.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 131,942.00