Dept. of Trans. PROGRESS Serial No. Contract No. 21-025-14-08 07-311704 PROGRESS PAYMENT VOUCHER %complete: %time: 2% 12% Location: Federal Project: 07-LA-134-0.0/R13.3 HSNH-P134(40) Progress payment No. 005 Payment period ending: 01-20-21 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 834,589.17 466,264.17 2. a. Extra Work 19,757.11 2,300.00 b. Adustment Comp. 3. Materials on Hand 72,777.00 -21,226.00 4. Earned Subject to Retention 927,123.28 447,338.17 5. Mobilization 6. Total Work Completed 854,346.28 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 927,123.28 447,338.17 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 447,338.17