Dept. of Trans. PROGRESS Serial No. Contract No. 21-111-19-24 07-311704 PROGRESS PAYMENT VOUCHER %complete: %time: 9% 19% Location: Federal Project: 07-LA-134-0.0/R13.3 HSNH-P134(40) Progress payment No. 008 Payment period ending: 04-20-21 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,296,218.72 1,148,614.90 2. a. Extra Work 29,743.48 6,291.82 b. Adustment Comp. 3. Materials on Hand 40,226.00 -137.00 4. Earned Subject to Retention 3,366,188.20 1,154,769.72 5. Mobilization 387,500.00 0.00 6. Total Work Completed 3,713,462.20 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 3,753,688.20 1,154,769.72 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,154,769.72