Dept. of Trans. PROGRESS Serial No. Contract No. 21-293-11-55 07-311704 PROGRESS PAYMENT VOUCHER %complete: %time: 32% 40% Location: Federal Project: 07-LA-134-0.0/R13.3 HSNH-P134(40) Progress payment No. 014 Payment period ending: 10-20-21 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,810,338.39 1,024,312.92 2. a. Extra Work 79,536.06 0.00 b. Adustment Comp. 3. Materials on Hand 458,849.83 0.00 4. Earned Subject to Retention 12,348,724.28 1,024,312.92 5. Mobilization 736,250.00 0.00 6. Total Work Completed 12,626,124.45 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 13,084,974.28 1,024,312.92 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,024,312.92