Dept. of Trans. PROGRESS Serial No. Contract No. 22-111-12-56 07-311704 PROGRESS PAYMENT VOUCHER %complete: %time: 44% 55% Location: Federal Project: 07-LA-134-0.0/R13.3 HSNH-P134(40) Progress payment No. 020 Payment period ending: 04-20-22 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 16,907,683.33 869,203.66 2. a. Extra Work 139,920.04 0.00 b. Adustment Comp. 3. Materials on Hand 623,234.10 -26,134.76 4. Earned Subject to Retention 17,670,837.47 843,068.90 5. Mobilization 736,250.00 0.00 6. Total Work Completed 17,783,853.37 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 18,407,087.47 843,068.90 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 843,068.90