Dept. of Trans. PROGRESS Serial No. Contract No. 23-232-12-49 07-311704 PROGRESS PAYMENT VOUCHER %complete: %time: 81% 89% Location: Federal Project: 07-LA-134-0.0/R13.3 HSNH-P134(40) Progress payment No. 036 Payment period ending: 08-20-23 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 30,618,498.98 403,839.00 2. a. Extra Work 408,811.67 3,914.95 b. Adustment Comp. 3. Materials on Hand 1,186,755.91 -188,990.00 4. Earned Subject to Retention 32,214,066.56 218,763.95 5. Mobilization 775,000.00 0.00 6. Total Work Completed 31,802,310.65 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 32,989,066.56 218,763.95 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 218,763.95