Dept. of Trans. PROGRESS Serial No. Contract No. 23-261-10-40 07-311704 PROGRESS PAYMENT VOUCHER %complete: %time: 82% 92% Location: Federal Project: 07-LA-134-0.0/R13.3 HSNH-P134(40) Progress payment No. 037 Payment period ending: 09-20-23 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 31,158,757.66 540,258.68 2. a. Extra Work 408,811.67 0.00 b. Adustment Comp. 3. Materials on Hand 1,183,868.98 -2,886.93 4. Earned Subject to Retention 32,751,438.31 537,371.75 5. Mobilization 775,000.00 0.00 6. Total Work Completed 32,342,569.33 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 33,526,438.31 537,371.75 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 537,371.75