Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 23-146-11-41 07-311904 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 07-LA-605-R0.0/26.0 HSNH-X037(214) Progress payment No. 028 Payment period ending: 05-02-23 CROSSTOWN ELECTRICAL & DATA INC 5454 DIAZ ST IRWINDALE CA 91706 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 6,260,300.00 36,335.20 2. a. Extra Work 321,881.90 14,296.49 b. Adustment Comp. -122,680.30 0.00 3. Materials on Hand 4. Earned Subject to Retention 6,459,501.60 50,631.69 5. Mobilization 411,600.00 0.00 6. Total Work Completed 6,871,101.60 7. Deductions -110,000.00 -30,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 6,761,101.60 20,631.69 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 20,631.69