Dept. of Trans. PROGRESS Serial No. Contract No. 21-355-15-50 07-312004 PROGRESS PAYMENT VOUCHER %complete: %time: 53% 72% Location: Federal Project: 07-LA-110-0.7/26.1 HSNH-X037(218) Progress payment No. 017 Payment period ending: 12-20-21 TEICHERT ENERGY & UTILITIES GROUP INC 3500 AMERICAN RIVER DRIVE SACRAMENTO CA 95864 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,291,057.32 322,865.73 2. a. Extra Work 2,861,960.82 0.00 b. Adustment Comp. 3. Materials on Hand 772,017.86 0.00 4. Earned Subject to Retention 13,925,036.00 322,865.73 5. Mobilization 2,000,000.00 100,000.00 6. Total Work Completed 15,153,018.14 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 15,925,036.00 422,865.73 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 422,865.73