Dept. of Trans. PROGRESS Serial No. Contract No. 23-324-22-38 07-312004 PROGRESS PAYMENT VOUCHER %complete: %time: 87% 100% Location: Federal Project: 07-LA-110-0.7/26.1 HSNH-X037(218) Progress payment No. 039 Payment period ending: 11-20-23 TEICHERT ENERGY & UTILITIES GROUP INC 3500 AMERICAN RIVER DRIVE SACRAMENTO CA 95864 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 19,833,138.78 270,296.43 2. a. Extra Work 3,223,710.19 0.00 b. Adustment Comp. 3. Materials on Hand 341,483.10 -77,104.20 4. Earned Subject to Retention 23,398,332.07 193,192.23 5. Mobilization 2,000,000.00 0.00 6. Total Work Completed 25,056,848.97 7. Deductions -10,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 25,388,332.07 193,192.23 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 193,192.23