Dept. of Trans. PROGRESS Serial No. Contract No. 19-022-11-03 07-312304 PROGRESS PAYMENT VOUCHER %complete: %time: 10% 10% Location: Federal Project: 07-LA-14-25.0/35.0 ACNH-P014(78) Progress payment No. 003 Payment period ending: 01-20-19 CHUMO CONSTRUCTION INC 14425 JOANBRIDGE ST BALDWIN PARK CA 91706 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 206,219.36 23,088.28 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 25,741.00 25,741.00 4. Earned Subject to Retention 231,960.36 48,829.28 5. Mobilization 162,500.00 0.00 6. Total Work Completed 368,719.36 7. Deductions -10,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 384,460.36 38,829.28 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 38,829.28