Dept. of Trans. PROGRESS Serial No. Contract No. 19-081-13-52 07-312304 PROGRESS PAYMENT VOUCHER %complete: %time: 16% 20% Location: Federal Project: 07-LA-14-25.0/35.0 ACNH-P014(78) Progress payment No. 005 Payment period ending: 03-20-19 CHUMO CONSTRUCTION INC 14425 JOANBRIDGE ST BALDWIN PARK CA 91706 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 360,987.32 43,696.46 2. a. Extra Work 10,059.17 0.00 b. Adustment Comp. 3. Materials on Hand 71,030.00 2,501.00 4. Earned Subject to Retention 442,076.49 46,197.46 5. Mobilization 243,750.00 0.00 6. Total Work Completed 614,796.49 7. Deductions -10,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 675,826.49 46,197.46 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 46,197.46