Dept. of Trans. PROGRESS Serial No. Contract No. 19-204-10-14 07-312504 PROGRESS PAYMENT VOUCHER %complete: %time: 13% 15% Location: Federal Project: 07-LA-5-81.8/87.8 ACIM-005-3(126) Progress payment No. 002 Payment period ending: 07-20-19 POWELL CONSTRUCTORS INC 8555 BANANA AVE FONTANA CA 92335 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 384,566.80 269,001.80 2. a. Extra Work 11,438.44 11,438.44 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 396,005.24 280,440.24 5. Mobilization 205,000.00 205,000.00 6. Total Work Completed 601,005.24 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 601,005.24 485,440.24 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 485,440.24