Dept. of Trans. PROGRESS Serial No. Contract No. 19-142-15-11 07-313304 PROGRESS PAYMENT VOUCHER %complete: %time: 81% 84% Location: Federal Project: 07-VEN-23-1.4/31.7 NONE Progress payment No. 006 Payment period ending: 05-20-19 RSB GROUP INC 20331 LAKE FOREST DR #C-13 LAKE FOREST CA 92630 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 626,472.00 173,667.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 626,472.00 173,667.00 5. Mobilization 85,000.00 0.00 6. Total Work Completed 711,472.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 711,472.00 173,667.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 173,667.00