Dept. of Trans. PROGRESS Serial No. Contract No. 20-056-10-43 07-313804 PROGRESS PAYMENT VOUCHER %complete: %time: 97% 50% Location: Federal Project: 07-LA-110-11.0/11.0 NONE Progress payment No. 003 Payment period ending: 02-20-20 BEADOR CONSTRUCTION COMPANY 26320 LESTER CIR CORONA CA 92883 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 916,323.00 84,240.00 2. a. Extra Work 34,676.76 34,676.76 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 950,999.76 118,916.76 5. Mobilization 105,000.00 0.00 6. Total Work Completed 1,055,999.76 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,055,999.76 118,916.76 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 118,916.76