Dept. of Trans. PROGRESS Serial No. Contract No. 24-295-14-00 07-316004 PROGRESS PAYMENT VOUCHER %complete: %time: 43% 45% Location: Federal Project: 07-LA-14-R60.7/R77.0 NONE Progress payment No. 018 Payment period ending: 10-20-24 GUY F ATKINSON CONSTRUCTION LLC 611 ANTON BLVD #1100 COSTA MESA CA 92626 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 54,044,766.26 -361,228.32 2. a. Extra Work 7,373,905.63 4,508,929.57 b. Adustment Comp. 476,888.94 6,245.61 3. Materials on Hand 1,247,234.08 -1,805.24 4. Earned Subject to Retention 63,142,794.91 4,152,141.62 5. Mobilization 10,818,837.50 0.00 6. Total Work Completed 72,714,398.33 7. Deductions -14,045.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 73,947,587.41 4,152,141.62 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 4,152,141.62