Dept. of Trans. PROGRESS Serial No. Contract No. 25-021-10-55 07-316004 PROGRESS PAYMENT VOUCHER %complete: %time: 51% 53% Location: Federal Project: 07-LA-14-R60.7/R77.0 NONE Progress payment No. 021 Payment period ending: 01-20-25 GUY F ATKINSON CONSTRUCTION LLC 611 ANTON BLVD #1100 COSTA MESA CA 92626 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 63,953,104.48 2,450,282.67 2. a. Extra Work 9,566,557.79 42,670.51 b. Adustment Comp. 1,521,118.83 50,244.28 3. Materials on Hand 1,536,200.40 9,924.45 4. Earned Subject to Retention 76,576,981.50 2,553,121.91 5. Mobilization 10,818,837.50 0.00 6. Total Work Completed 85,859,618.60 7. Deductions -14,045.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 87,381,774.00 2,553,121.91 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,553,121.91