Dept. of Trans. PROGRESS Serial No. Contract No. 25-141-11-30 07-316004 PROGRESS PAYMENT VOUCHER %complete: %time: 63% 64% Location: Federal Project: 07-LA-14-R60.7/R77.0 NONE Progress payment No. 025 Payment period ending: 05-20-25 GUY F ATKINSON CONSTRUCTION LLC 611 ANTON BLVD #1100 COSTA MESA CA 92626 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 84,228,708.16 5,210,843.35 2. a. Extra Work 11,111,123.86 232,549.81 b. Adustment Comp. 1,269,416.74 -297,378.62 3. Materials on Hand 2,399,422.24 14,293.42 4. Earned Subject to Retention 99,008,671.00 5,160,307.96 5. Mobilization 11,388,250.00 0.00 6. Total Work Completed 107,997,498.76 7. Deductions -14,045.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 110,382,876.00 5,160,307.96 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 5,160,307.96