Dept. of Trans. PROGRESS Serial No. Contract No. 25-199-11-56 07-316004 PROGRESS PAYMENT VOUCHER %complete: %time: 66% 68% Location: Federal Project: 07-LA-14-R60.7/R77.0 NONE Progress payment No. 027 Payment period ending: 07-20-25 GUY F ATKINSON CONSTRUCTION LLC 611 ANTON BLVD #1100 COSTA MESA CA 92626 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 93,880,471.92 5,702,551.21 2. a. Extra Work 11,340,094.02 225,357.74 b. Adustment Comp. 1,251,558.28 50,231.44 3. Materials on Hand 1,976,509.39 -400,213.79 4. Earned Subject to Retention 108,448,633.61 5,577,926.60 5. Mobilization 11,388,250.00 0.00 6. Total Work Completed 117,860,374.22 7. Deductions -14,045.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 119,822,838.61 5,577,926.60 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 5,577,926.60