Dept. of Trans. PROGRESS Serial No. Contract No. 25-233-15-54 07-316004 PROGRESS PAYMENT VOUCHER %complete: %time: 70% 72% Location: Federal Project: 07-LA-14-R60.7/R77.0 NONE Progress payment No. 028 Payment period ending: 08-20-25 GUY F ATKINSON CONSTRUCTION LLC 611 ANTON BLVD #1100 COSTA MESA CA 92626 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 101,717,800.00 7,837,328.10 2. a. Extra Work 11,340,094.02 0.00 b. Adustment Comp. 995,344.41 -256,213.87 3. Materials on Hand 1,233,907.20 -742,602.19 4. Earned Subject to Retention 115,287,145.63 6,838,512.04 5. Mobilization 11,388,250.00 0.00 6. Total Work Completed 125,441,488.43 7. Deductions -14,045.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 126,661,350.63 6,838,512.04 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 6,838,512.04