Dept. of Trans. PROGRESS Serial No. Contract No. 25-260-18-28 07-316004 PROGRESS PAYMENT VOUCHER %complete: %time: 73% 75% Location: Federal Project: 07-LA-14-R60.7/R77.0 NONE Progress payment No. 029 Payment period ending: 09-20-25 GUY F ATKINSON CONSTRUCTION LLC 611 ANTON BLVD #1100 COSTA MESA CA 92626 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 106,722,442.50 5,004,642.49 2. a. Extra Work 11,968,851.23 628,757.21 b. Adustment Comp. 803,316.05 -192,028.36 3. Materials on Hand 1,182,933.70 -50,973.50 4. Earned Subject to Retention 120,677,543.48 5,390,397.84 5. Mobilization 11,388,250.00 0.00 6. Total Work Completed 130,882,859.78 7. Deductions -14,045.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 132,051,748.48 5,390,397.84 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 5,390,397.84